「英中对照」多重制约因素延缓亚太地区数据中心建设扩张热潮
Speed Bumps Slow Asia-Pacific’s Data Center Gold Rush
亚太地区数据中心建设扩张热潮近期遭遇融资遇冷、监管收紧、供配电约束等多重制约,发展节奏有所放缓。据金融时报报道,本周澳大利亚新云厂商Firmus撤回规模71亿澳元的澳交所IPO申请,拟转而寻求最高30亿美元私募融资;菲律宾PLDT在交易所披露文件中称因市场环境及利率上升,将旗下数据中心REIT Vitro原预计最高募资242亿菲律宾比索的上市计划推迟至2027年。
材料汇总亚太数据中心行业近期在融资、项目推进、供配电保障方面的多重受阻信号,反映区域行业扩张节奏变化;相关项目后续安排、监管细则及企业融资进展需以官方披露为准。
Asia-Pacific's hectic data center rollout has hit a series of speed bumps. The most dramatic by far was the collapse Friday of Australian-based Firmus’ planned AU$7.1 billion (US$4.97 billion) IPO, which had been expected to be the biggest ASX debut since Telstra’s 1997 IPO.
Firmus, a neocloud company whose shareholders include Blackstone, Jane Street and Nvidia, withdrew its ASX listing application Friday and said it would seek up to $3 billion through private fund-raising, the Financial Times has reported.
It had struggled to win market support at its target price of around AU$11 ($7.67), but even after it offered to cut the price, investors did not have the appetite.
Trading in Maas Group, one of Firmus' shareholders, was halted Friday after the stock dropped 27% in two days. Maas Group has a 3.2% stake in the company as well as outstanding contracts with Firmus worth AU$727 million ($507 million).
Related:Nvidia’s $500B AI Infrastructure Bet Raises Power Stakes
Two days earlier, Firmus had been dumped by CDC Data Centers from their joint AI infrastructure project in Australia after CDC had become troubled by Firmus’ southeast Asian expansion, which had not been a part of the original partnership.
PLDT delays IPO to 2027
Firmus' wasn't the only IPO to go south this week. Philippine telco PLDT put its data center REIT listing on hold until 2027, blaming the decision on higher interest rates. The REIT, Vitro, was expected to generate as much as 24.2 billion Philippine pesos (US$385.1 million) on the Manila bourse.
PLDT said in an exchange filing it had decided to delay the IPO until 2027 due to "current market conditions and rising interest rates." But it said it was committed to the IPO as an important part of its asset monetization and deleveraging plans.
The Philippines' central bank last month hiked interest rates by 25 basis points and is widely expected to announce two more rate rises by the year's end.
Southeast Asian governments have also been forced to press pause on the AI boom. Last week, Indonesia's West Java province halted a 640MW project by Singapore–based BDX, claiming it had not received key approvals, including an environmental assessment.
A month ago, Thailand suspended 166 data center projects – of which 49 were under construction and 117 awaited approval – to allow government committees to write new industry rules that would set standards and maximize the economic benefit to Thailand.
In Malaysia, the center of Asia's data center boom, officials are anxious about soaring the new digital infrastructure's power consumption. Electricity demand growth has gone from 1.5%-2% annually to nearly 10% due to data centers, Siti Safinah Salleh, head of the Malaysian Energy Commission, is reported to have said.
Related:AI Is Redefining Data Center Ownership: Multiple Assets, Multiple Timelines
Salleh warned that recovering energy costs from data center operators is difficult because many are on short-term contracts and have refused to make long-term commitments.
This article was originally published on Light Reading.
About the Authors
Contributing Editor, Light Reading
Robert Clark is a Contributing Editor at Light Reading.
来源:Data Center Knowledge 数据中心行业 · datacenterknowledge.com