「英中对照」历时13年、耗资20亿美元的纽约乔治·华盛顿大桥修复计划完成11个项目中的第8个

13-year, $2B NYC bridge rehab completes 8th of 11 projects

AI 导读

纽约与新泽西港务局10月15日宣布重新开放乔治·华盛顿大桥南步行道,今后行人专用南道、骑行者专用北道。该工程属Skanska 4.52亿美元更换大桥592根吊索合同的一部分,重建了1.5英里步行道,引道最宽14英尺、坡度不超5%,并在纽约端新增观景平台、新泽西端扩建入口广场。

正文 · 原文

An article from

Dive Brief

Skanska’s $452 million contract to replace the bridge’s 592 suspender ropes included the 1.5-mile pedestrian pathway rebuild.

Published Oct. 16, 2026

Sebastian Obando's headshot

The Port Authority of New York and New Jersey ceremony on Oct. 15, 2026

The Port Authority of New York and New Jersey held a ceremony on Oct. 15, 2026, to announce the reopening of the South Walk of the George Washington Bridge in New York City, N.Y. Courtesy of Port Authority of New York and New Jersey

This audio is auto-generated. Please let us know if you have feedback.

Dive Brief:

Dive Insight:

The Port Authority has now completed eight of the program’s 11 phases, with two more ongoing and the last component planned, according to the release.

The renovated walkway features approach paths as wide as 14 feet and slopes no greater than 5%, according to the Port Authority. The work also added a new viewing platform at the New York entrance and an expanded entry plaza in New Jersey.

“The team developed hoisting systems that could be safely utilized with no disruption to normal bridge traffic,” David Murawski, senior vice president of operations at Skanska USA Civil, told Construction Dive. “The custom designed temporary work platforms suspended from the main cable worked in conjunction with the hoisting systems to provide safe and efficient access to all work locations.”

The South Walk closed in February 2023 due to the suspender rope replacement work, during which pedestrians and cyclists temporarily shared the North Walk. Under the new arrangement, pedestrians will now have dedicated use of the South Walk, while cyclists will exclusively use the North Walk.

“Because the anchor points for the suspender ropes were below the sidewalk, it had to be removed first in order to replace the suspenders,” said Murawski. “Once the suspenders were replaced, the sidewalk was restored.”

Skanska will still stay on the site for the next several months to remove temporary conduit and perform extra electrical work, he added. 

Other recently completed phases of the Restoring the George program include the replacement of roadway finger joints and 32 deck panels at the bridge’s two towers. This year, teams also completed the rehabilitation of the upper-level eastbound roadway pavement and the ramps on 178th and 179th streets, according to the release.

Ongoing projects include the rehabilitation of the Center Avenue and Lemoine Avenue bridges, as well as the rehabilitation of lower-level steel and replacement of movable maintenance platforms, according to the release.

To wrap up the 11-project program, the Port Authority also plans to rehabilitate components of the Fort Washington Avenue, Broadway, Wadsworth Avenue, St. Nicholas Avenue, Audubon Avenue and Amsterdam Avenue bridges over the Trans-Manhattan Expressway, according to the release.