「英中对照」JLL:建设成本年涨幅3%至6%成新基线,数据中心开发商利润承压
Data Center Developers Face Tighter Margins as Construction Costs Rise
JLL在《2026年全球建设成本指数》中称,建设成本年涨幅3%至6%已成为新基线,高于2020年前的2%至3%,数据中心开发商只有在具备电力接入、已承诺客户和可信交付路径时才能将上涨成本转嫁给租户。
JLL给出的成本涨幅基线和2027年投标价格预测会影响数据中心项目的可行性评估、采购节奏与用工安排;但其预测针对整体建筑业而非数据中心专项,且成本能否转嫁取决于电力接入、租约结构等条件,具体项目影响仍需逐一核验。

JLL says annual construction cost escalation of 3% to 6% is now the baseline, up from 2% to 3% before 2020.Getty Images
Data center developers may be able to pass higher construction costs on to tenants, but only when projects have power access, committed customers, and a credible path to delivery, according to JLL.
In its Global Construction Costs Index 2026, the real estate services firm said annual construction cost escalation of 3% to 6% has become the new baseline, up from the 2% to 3% range common before 2020. JLL also forecasts another 3.1% to 4.2% increase in global tender prices in 2027, including 3.2% to 4.2% in North America. Those forecasts apply to construction broadly rather than the data center sector alone.
The JLL report notes that rising rents and asset values have helped data center projects absorb some of that inflation. However, Matthew Giddings, executive director of technical services with JLL’s Data Centers and Critical Environments team, said stronger market fundamentals do not automatically protect individual projects.
Related:Vertical Data Centers Face Cost-Proximity Trade-Offs
“The economics break down when costs outpace contracted revenue or power delays postpone income while financing costs continue to accumulate,” Giddings told Data Center Knowledge. “Higher asset values alone cannot close that gap.”
That risk is most acute for speculative campuses without anchor tenants, projects with uncertain power delivery, and developments tied to fixed-rent agreements that leave little room to absorb construction escalation. Older facilities being repositioned for AI workloads may also face difficult economics if upgrades become too extensive.
“Strong demand supports the market, but it does not make every project viable,” Giddings said.
Developers should reassess projects when rising capital costs erode expected returns, utility schedules slip beyond committed occupancy dates, or tenant demand no longer supports planned capacity, he said. Reduced power availability and delays in anchor-tenant commitments are also signs that a project may need to be reworked.
One way to manage that risk is through phased construction. By aligning spending with confirmed electricity supply and customer demand, developers can limit the amount of capital they commit before fundamentals are in place.
Skilled Trades Constrain Delivery
Labor constraints are adding to the pressure. Giddings said the electrical and mechanical trades are creating the greatest cost and schedule challenges, particularly electricians, high-voltage specialists, pipefitters, and advanced cooling technicians.
“Controls, commissioning, and startup teams have also become critical bottlenecks, as their availability often determines when a completed facility can be placed into service,” he noted.
Related:How to Secure Data Centers During the Construction Phase
Competition for utility and substation construction crews is also intensifying, adding risks that extend beyond the data center site itself. To reduce exposure, Giddings recommended that developers bring in trade partners early and test project schedules against real workforce availability rather than assumed labor capacity.
He also pointed to standardized designs, off-site prefabrication, and phased construction as ways to reduce peak labor requirements. In remote markets, developers may need to offer housing, transportation, and travel incentives to attract workers. In the longer term, investment in trade schools, apprenticeships, and union training facilities could help support future construction phases while expanding local employment opportunities, he said.
Buy Early Without Freezing the Design
Procurement strategy is becoming just as important. Long lead times for critical equipment have pushed many developers to place orders earlier, but doing so can create problems if tenant requirements shift, particularly as AI infrastructure continues to evolve.
“The key is to secure manufacturing capacity early without freezing every design decision,” Giddings said.
Related:Virginia Tops AI Data Center Readiness Ranking as Smaller Markets Advance
He said developers should reserve production slots for transformers, switchgear, generators, and cooling equipment while negotiating flexibility to modify specifications before fabrication begins. Orders should advance in line with validated tenant requirements and clear decision deadlines.
That approach is especially important as operators try to account for shifting rack densities and growing interest in liquid cooling. Modular power and cooling systems, built-in expansion capacity, and design provisions for liquid cooling can help facilities adapt without undermining the overall project.
“Early procurement protects the schedule, while flexible design protects the long-term value of the asset,” Giddings said.
Retrofitting older facilities can offer another path to faster delivery and lower upfront costs, particularly when a site already has available power, sufficient structural capacity, and infrastructure that can be reused. However, those advantages can disappear quickly if a building requires major mechanical upgrades, higher electrical distribution capacity, heavier floor loading, or large-scale liquid-cooling retrofits.
“The economics ultimately depend on how much existing infrastructure can be retained while still meeting current and future performance requirements,” Giddings said.
About the Author
Contributor
Nathan Eddy covers data center trends and technologies across multiple industries. A graduate of Northwestern University’s Medill School of Journalism, he is also a documentary filmmaker specializing in architecture and urban planning. He currently lives in Berlin, Germany.